OKG

Unit Oskarshamn 3 Restarted

Pressrelease Monday, December 21, 2015

Early in the morning of 19 December, the electricity delivery at unit Oskarshamn 3 was resumed following only four days of downtime.

On the night before Tuesday 15 December, loss of voltage unexpectedly occurred on a collector rail in connection with preparations performed for a capacity test on a battery. Corrective measures were subsequently taken after the cause of the failure had been analysed. Since the work proceeded better than expected, it was possible to restart unit O3 in the morning of 19 December, nearly three days earlier than initially assessed.

Press contact

Communications and Public Relations

E-mail: info@okg.uniper.energy

Phone: +46 491-78 75 50

Page updated Monday, December 21, 2015