OKG

Restart of Unit Oskarshamn 1 Postponed

Pressrelease Tuesday, May 17, 2016

The annual outage at unit Oskarshamn 1 was being completed on Saturday 14 May when the unit was synchronized to the offsite grid. However, the restart was suspended and the unit shut down for measures to be taken due to oil leakage on a flexible tube in the conventional turbine equipment and a leaking valve in the auxiliary condenser.

At present, intense activities are in progress in order to remedy the leakages, and synchronization to the grid is currently estimated to take place later this week.

For further information on any changes, please see the website of the Nordic Power Exchange, nordpoolspot.com. You can also find updated production information on our website About our production.

Press contact

Communications and Public Relations

E-mail: info@okg.uniper.energy

Phone: +46 491-78 75 50

Page updated Tuesday, May 17, 2016